Heavy Industry » PROJECTS IN GREECE » TURN AROUND PROJECTS » REVAMPING OF FUEL & PETROL UNITS & EQUIPMENT OF GENERAL SHUT DOWN

Description

REVAMPING OF FUEL & PETROL UNITS & EQUIPMENT OF GENERAL SHUT DOWN

 

Project      

:

Revamping of fuel & petrol units & equipment of GENERAL SHUT DOWN

Owner

:

Motor Oil Hellas

Contract

:

2402128 – 17/04/2016

Duration

:

2 months preparation, 14 days S/D

Budget

:

2.158.627,00 €

Brief description

 

:

The project was executed in the Motor Oil (Hellas) Refinery in Corinthos, during the GSD 2016 and included the following works:

a. Maintenance works of the equipment in the units U-1100/ 1200/ 1300/ 4200/ 4950/ 7300/ 7700/ 2100/ 2200/ 2500/ 2600/ Η-4701-Ν

§  Installation of scaffolding all around equipment internally and externally in the positions of operations.

  • Installation of blinds of the isolation of the units and restoration after the end of the maintenance.
  • Opening of equipment externally and internally for inspection: towers, reactors, regenerator, filters, furnaces, vessels.
  • Works in Furnace F-1101.
    • Replacement of steam air preheater and air preheater Ε-1152 (Weight     80.000 kg).
    • Replacement of roof panels in Radiant section
    • Restoration – maintenance of refractories.
    • Replacement of tube supports.
  • Repair of Thermal Reactor Package F-7701/E-7701.
    • Removal of refractories, internal cleaning with sandblasting.
    • Partial Replacement of the Shell of F-7701, X-rays and PWHT in 100% of the weldings
    • Tube replacement in Ε-7701. Total tubes 247 pieces of diameter 1 1/2"
    • Restoration of refractories F-7701.
    • Closing and restoration of Thermal reactor Package.
  • Inspection of Vessels/ Tanks/ Seals.
  • Exchangers – Air coolers

Opening, bundle extraction or replacement, repairs, pressure tests, restoration.

  • Replacement of 2 flare tips of Fuels and Lubricants Units.
  • Tank Τ-7701 replacement (Diameter 3,7m, Length 19,5m, Weight 54 tons).
  • Tower C-4201 Replacement (Diameter 0,85m, Height 20m, Weight 11 tons).
  • Maintenance totally in 5 towers, 3 reactors, 4 furnaces, 55 exchangers, 10 air cooler, 20 vessels, 6 tanks, 2 seals, 2 flare tips.

b. Piping Works

  • Maintenance works and new projects Piping works for products and utilities.

Prefabrication and erection of piping during shut down, partial line replacements, installing new lines

Lines Diameter: 1/2" ÷ 36", width to 11mm, materials C.S., Stainless steel.

Total dia inches: 2300.

Quality Control: X-Rays 20%

Pressure test of piping: 20 bar ÷ 120 bar.

c. All type Valves replacement from 1" ÷ 24". Total pieces 156.    

The 91% of the work was done during the S/D.

All the materials and equipment was provided by the owner except the materials for the new piping supports.

The works executed for 2 months before and 21 days during S/D.

The above project was executed in parallel with the projects ‘’ Unit revamping FCC/ 3100/ 3700 & equipment of GENERAL SHUT DOWN ‘’ and ‘’ Revamping works in  fuels, petrol, FCC units’’ on the same Shut Down period 2016.

 

 
<< Previous  |   Next >>

Cookies are small text files that are stored in our browser while browsing the web. Their purpose is to notify the site that the user visits for his previous activity. They typically describe our username and password when we visit the same site later, remember us and do not need to login.
 

Learn More ...

These are the cookies used by our website to improve your browsing and temporarily store your preferences.

Disabling them is likely to cause problems in viewing the site .

You can set your browser to block or alert you to these cookies, but some parts of the site will not work properly.