Project
|
:
|
Repairs on crude & gasolines pipelines at HEL.PE/E.I.C.
|
Owner
|
:
|
Hellenic Petroleum S.A.
|
Contract
|
:
|
16/12/2010
|
Duration
|
:
|
6 months
|
Budget
|
:
|
140.396,85 €
|
Brief description
|
:
|
The project was executed at the industrial complex of Hellenic Petroleum, in Elefsina Attica and included the following works:
- Field measurements.
- Prefabrication of piping.
- Piping erection.
- Fabrication and erection of steel structures (equipment attics, pipe routing ways, pipe supports, etc.).
- Sandblast and painting of pipes - equipment and steel structures.
- Networks insulation using rockwool.
The works on piping related to products networks and utility lines and were performed on all production and handling units of the refinery.
Pipe sections ranged from ½'' - 24'' and materials were C.S.
All main piping materials and equipment were provided by Hellenic Petroleum.