Heavy Industry » PROJECTS IN GREECE » PORTS - ENERGY PROJECTS » SUBSEA UNLOADING PIPELINE 8'' MAINTENANCE WORKS

Description

SUBSEA UNLOADING PIPELINE 8'' MAINTENANCE WORKS [245]

Project  

:

Subsea unloading pipeline 8" maintenance works

Owner

:

Rhodes-Alexandroupolis Oil Products Facilities SA

Contract

:

30/5/2002

Duration

:

10 calendar days

budget

:

108,000.00 €

Brief description

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

:

The project was  executed at the facilities of Alexandroupolis of the company "Rhodes-Alexandroupolis Oil Products Facilities SA" and included the following works:

§     Excavation and surfacing of a sub-sea segment of pipe 8" at a length of 200m and removal of all boulder stones and pipe fixing elements (excavation of trench employing divers)

§     Partial floating off of the pipe using float means (float cranes, tugboats, divers)

§     Cutting of the last edge of the pipe at a length of 40m and welding of a new pipe, 100% X-R welds inspections.

§     Total inspection of the fuel unloading pipe

§     Setting, within the sub-sea trench, installation of all boulders and fixing elements of pipes and delivery in operational status

All pipe materials were supplied by the Owner

 

PROJECT CERTIFICATION

 
<< Previous  |   Next >>

Cookies are small text files that are stored in our browser while browsing the web. Their purpose is to notify the site that the user visits for his previous activity. They typically describe our username and password when we visit the same site later, remember us and do not need to login.
 

Learn More ...

These are the cookies used by our website to improve your browsing and temporarily store your preferences.

Disabling them is likely to cause problems in viewing the site .

You can set your browser to block or alert you to these cookies, but some parts of the site will not work properly.