Heavy Industry » PROJECTS IN GREECE » TURN AROUND PROJECTS » TOTAL TUBE REPLACEMENT ON ECONOMIZERS GROUP I & GROUP II AT THE BOILERS Κ - 1001 C/D

Description

TOTAL TUBE REPLACEMENT ON ECONOMIZERS GROUP I & GROUP II AT THE BOILERS Κ - 1001 C/D [2005]

 

Project     

:

Total tube replacement on economizer Group I & Group II at the boiler K-1001 C/D

Owner

:

Hellenic Petroleum SA

Contract

:

14 / 03 / 2011

Duration

:

6 months. Turn around (T/A) 31 days

Budget

:

273,121.85

Brief description

:

The project was  executed at the industrial  complex of Hellenic Petroleum, Aspropyrgos, Attica, and included the following works:

Supply of all materials for tubes and supports, prefabrication of 36   coils for boilers Κ-1001 C/D, prefabrication of all supports of coils made of stainless steel.

On the spot opening of economizers, dismantling of old  coils, mounting of new coils and  connection with the existing tubes, quality control, hydraulic test at 80 bar, restoration and commissioning

The works were carried out in two phases (one for each boiler) with turn-around duration of 31 days.

Tubes: Φ 38mm * 2.9mm thickness (ST 35.8 / III DIN 17175).

Total  welding joints: 993 pcs

 

 

PROJECT CERTIFICATION

 
<< Previous  |   Next >>

Cookies are small text files that are stored in our browser while browsing the web. Their purpose is to notify the site that the user visits for his previous activity. They typically describe our username and password when we visit the same site later, remember us and do not need to login.
 

Learn More ...

These are the cookies used by our website to improve your browsing and temporarily store your preferences.

Disabling them is likely to cause problems in viewing the site .

You can set your browser to block or alert you to these cookies, but some parts of the site will not work properly.