The works were carried out at the Skaramangas pier and inside the Aspropyrgos facilities of BP Hellas and included the following:
1. Skaramangas pier
§ Placement of new parts at the oil pipe line at the main rig
§ Replacement of parts of the gasoline loading arm at the main rig
§ Replacement of parts of gasoline lines
§ Construction of new pipe line network for products at the main rig
§ Replacement of foam pipes, installation of new drain lines, construction of new fire fighting water supply line, replacement of lines and drain valves
§ Construction and installation of fire extinguishing central line at the pedestrian way of the pier, replacement of fire extinguishing line of 8’’ on the main rig, replacement of hydrants, replacement of water-foam hydrants
§ Construction and installation of pressurized air line
2. Inside the facility
§ Construction works of new pipes for the connection of Phase B pump station and reception network at tanks Nο. 10, 11, 13
§ Various maintenance works for the operation of pump stations and tanks
The works at Skaramangas pier were carried out using floating means.
Pipe networks: c.s. 1"÷16".
The equipment and the materials for pipe networks were supplied by the owner.
The metal profiles for the steel structures and supports, the materials of construction works, wherever carried out, as well as the sand blasting-painting materials were supplied by our company.
All works were carried out without any interruption to the smooth operation of the facilities.
|