Project
|
:
|
Partial replacement of underground gasoline, diesel and jet pipelines from tank farm to pier.
|
Owner
|
:
|
ΒP Hellas SA
|
Contract
|
:
|
2006
|
Duration
|
:
|
6 months
|
Budget
|
:
|
519,116.00 €
|
Brief description
|
:
|
The works were carried out at the facilities of BP Hellas, in Aspropyrgos, Attica, and included the following:
§ Partial replacement of the three reception pipes (12’’ for gasoline, 16’’ for petroleum and 16’’ for Jet A1) from the Aspropyrgos facilities to pier, at the DEPA SA’s passage location, and inside the facility, near the loading entrance of the Hellenic Petroleum SA
§ Rearrangement works of pipes at the reception system from the pier
The works included all civil works (earth and cement works, shoring up etc).
The materials for the pipe networks were supplied by the owner, the materials related to civil works by our company.
|
|
|
|
|
|
|
|
|