The works were carried out at the regional facilities in the area of Linoperamata of Crete, in Igoumenitsa, in Kalamata, in Thessaloniki, and included the following:
1. Linoperamata, Crete, facility
§ Construction of product lines of tanks No 10 and 13, reconstruction of parts of product lines of tanks No 12/4/5/6, modifications of lines at tank basin No 12
§ Replacement of lines at the basin tunnel of tanks No 1, 2
§ Replacement of central line at the pump station and on either side of the tank road
§ Replacement of Jet A1 lines at the Pig station
§ Replacement of fire extinguishing lines of tank No 13, water line at tank No 18, modifications of fire extinguishing pump station
§ Replacement of oil/water separation lines of tank basins
§ Various steel structures and supports
2. Corfu facility
§ Installation of new reception fuel pipe of the Gouvies facility
The works included all building and mechanical works for the complete replacement of the underground reception line of 6’’ up to the pier.
§ Construction of fire extinguishing collector and other pipes at the Alykes facility
3. Igoumenitsa facility
§ Construction of fuel networks and replacement of sections of product lines
§ Improvement of fire extinguishing network
4. Kalamata facility
§ Replacement of fuel inlet pipes at the tanks and construction of new outlet pipes to loading lines
§ Modification of networks at the loading lines and tank pit
§ Construction of fire extinguisher collector and other fire extinguishing pipes
5. Thessaloniki facility
§ Dismantling and installation of central water supply branches to loading lines and replacement of water network lines
§ Line conversions at the pig station and air networks
§ Construction and installation of heaters at the access networks
Pipe networks: c.s. 1"÷16".
The equipment and the materials for pipe networks were supplied by the owner.
The metal profiles for the steel structures and supports, the materials of construction works, wherever carried out, as well as the sand blasting-painting materials were supplied by our company.
All works were carried out without any interruption to the smooth operation of the facilities.
|