Project
|
:
|
Interconnection of U-2600 with Merichem skids
|
Owner
|
:
|
Hellenic Petroleum SA
|
Contract
|
:
|
01 / 04 / 2010
|
Duration
|
:
|
4 months
|
Budget
|
:
|
246.729,00 €
|
Brief description
|
:
|
The project was executed at the industrial complex of Hellenic Petroleum, Aspropyrgos, Attica, and included the following works:
Civil works for the construction of foundations, prefabrication and erection of steel structures, equipment erection, prefabrication and construction of piping networks of petroleum products and utilities for the interconnection of the old and new equipment and electrical interconnection and instrument works
Furthermore, all necessary scaffolds were erected and all required sandblasting – painting works were carried out.
|
|
|
|
|
|
|
|
|