Project
|
:
|
Mechanical works for the infusion system of additives
|
Owner
|
:
|
Hellenic Fuels SA (former BP Hellas SA)
|
Contract
|
:
|
20 / 07 / 2010
|
Duration
|
:
|
3,5 months
|
Budget
|
:
|
310,176.00 €
|
Brief description
|
:
|
The project was executed at the industrial complex of Hellenic Fuels (former BP), in Aspropyrgos Attica and included the following works:
a. Construction of new pump station (8 pumps) of chemical additives and their connection with additive tanks and loading lines of petroleum products.
b. Changes, revamping and maintenance of existing additive equipment for inclusion in the new system
Piping networks: stainless steel & c.s.
All the equipment and the materials for pipe networks were supplied by the owner.
The metal profiles for the metal constructions and supports as well as the sand blasting-painting materials were supplied by our company.
All works were carried out without any interruption to the smooth operation of the facilities.
|
|
|
|
|
|
|
|
|