The works were carried out at the regional facilities of BP Hellas in Corfu, in Igoumenitsa and in Thessaloniki, and included the following:
1. Corfu facility
§ Replacement of jet pipe of pier at the salt marshes
§ Replacement of fuel lines from the pump station to the loading line at the salt marshes
§ Replacement of foam-water manifolds, cooling lines and cooling rings at the fuel tanks of the Gouvies facility
2. Igoumenitsa facility
§ Construction of new VRU base at the facility
It included the full dismantling of the whole VRU unit, the removal of the existing infrastructure-foundation, the construction of the new infrastructure and foundation of the Unit, the new assembly of the VRU unit (equipment, pipes, electrical works – instruments) and commissioning
§ Construction of pipe lines and pump station
3. Thessaloniki facility
§ Replacement of parts of reception line 8’’ at the pier. It included underground and ground parts
§ New construction of product lines 16’’ of tank No 10 and VRU of the facility
§ Pipe lines of delivery products at the loading lines
§ New constructions at the pump station of the facility
Pipe networks: c.s. 1»÷16».
The equipment and the materials for pipe networks were supplied by the owner.
The metal profiles for the steel structures and supports, the materials of construction works, wherever carried out, as well as the sand blasting-painting materials were supplied by our company.
All works were carried out without any interruption to the smooth operation of the facilities.
|