Project
|
:
|
18'' ballast pipeline replacement in pier No2
|
Owner
|
:
|
Hellenic Petroleum S.A.
|
Contract
|
:
|
26/07/2010
|
Duration
|
:
|
2 months
|
Budget
|
:
|
53.027,57 €
|
Brief description
|
:
|
The project was executed at the industrial complex of Hellenic Petroleum in Elefsina, Attica, and included the following works:
- Prefabrication of piping.
- Piping erection.
- Sandblast and painting of pipes.
Pipe sections ranged from ½'' - 18'' and materials were C.S.
All main piping materials and equipment were provided by Hellenic Petroleum.